Profit on cost once adjustment (step 3)
Contents: This section of the SSRO's guidance describes the profit on cost once adjustment, step 3 of the contract profit rate.
4.1 | Section 17(2) of the Act, and regulation 11(4), set out the requirement for the POCO adjustment:
|
4.3 | Section 30 of the Act sets out that “[the Act] and single source contract regulations apply to qualifying subcontracts (and to sub-contractors) as they apply to qualifying defence contracts (and to primary contractors)”. In the case of a qualifying sub-contract, the calculation of the POCO adjustment is agreed between the sub-contractor and the contracting authority, rather than the Secretary of State, and this guidance must be modified by reading references to the Secretary of State as the contracting authority and references to the contractor as the sub-contractor. |
4.4 | The POCO adjustment applies in the calculation of a contract profit rate if, at the time of the agreement, the primary contractor is party to, or proposes to enter into, a group sub-contract SSRO guidance: Time of agreement |
4.5 | Regulation 12(2) sets out that the POCO adjustment is zero if the Secretary of State is satisfied that the Allowable Costs of the qualifying defence contract have already been decreased by an amount equal to the attributable profit on all group and further group sub-contracts. |
4.6 | Regulation 12(3) sets out that, where the Secretary of State is not satisfied that the allowable costs have been adjusted to remove an amount equal to the attributable profit, a POCO adjustment may be agreed. The purpose of this guidance is to provide a consistent methodology for contractors and the Secretary of State to follow when agreeing a POCO adjustment. |
4.7 | The diagram below demonstrates when a POCO adjustment should be made. |
4.8 | The information upon which the POCO calculation is constructed is likely to be held by the prime contractor and their group sub-contractors and not the Secretary of State. In such cases, in order for the parties to reach an informed agreement as to the POCO adjustment:
|
4.9 | The table below demonstrates the process that contractors and the Secretary of State must have regard to when agreeing the POCO adjustment amount. Please refer to paragraph 4.10 onwards for a glossary of the terms used. And please refer to Appendix B for a high-level worked example of the process to aid users.
|
4.10 | As set out in regulation 12(5), “group sub-contract” means a contract:
|
4.11 | As set out in regulation 12(6), “further group sub-contract” means a contract:
|
4.12 | As set out in regulation 12(7) to (8), the “attributable profit” is:
However, attributable profit does not include:
|
4.13 | As set out in regulation 12(10), a “group sub-contractor” means a person with which the primary contractor makes a group sub-contract. |
B.3 | The diagram below reflects the expected price of the contract if profit on allowable sub-contract costs is only applied once as per section 15 of the Defence Reform Act. This is determined by:
|