Guidance on specific cost types
Contents: This section of the SSRO's allowable costs guidance provides additional guidance on the AAR principles for specific categories of cost including, in some cases, the types of evidence that should be considered.
SSRO Determination: In 2019 the SSRO issued a determination on the extent to which labour costs in a qualifying defence contract are Allowable. Link to full referral |
C.1.2 | The MOD may decide to award single source contracts without the need for marketing and sales activity. Section C.2 refers to guidance on bid costs which may be incurred by a contractor when bidding for a single source contract. Marketing and sales costs may either in total or in part be considered Allowable in a single source contract if they meet the AAR principles and deliver demonstrable benefit to the UK Government. |
C.1.3 | Financial benefit to the MOD should be demonstrated by showing that the inclusion of marketing and sales costs results in a lower rate or unit costs charged to the QDC or QSC than if marketing and sales costs were excluded. The reduction in costs should be at least equivalent to the marketing and sales costs claimed. A sound evidence base should be provided to show how proven successful orders have resulted (retrospective test) or are expected to result through forecast sales (prospective test) in increased throughput of activity which then leads to the cost reduction in the QDC or QSC. |
SSRO Determination: In 2016 the SSRO issued a determination on the extent to which sales and marketing costs in a qualifying defence contract are Allowable. Link to full referral |
C.2.1 | Bid costs are those costs incurred in pursuit of the expected award of a specific contractual outcome. Bid costs incurred by a contractor in pricing a QDC or QSC may be Allowable Costs under the resulting contract and may include the staff costs of preparing and reviewing proposals. As the length of time to develop proposals varies depending on the nature of the contract the SSRO does not determine a timeframe within which these costs would be incurred. |
C.2.2 | Bid costs, where possible, should be charged directly to a contract although it is recognised that in some cases they may need to be apportioned as indirect costs. If no contract is awarded for which bid costs have been incurred these costs would generally not be Allowable as there is no QDC or QSC to which they would relate. However, the MOD and contractor may agree if and how any costs are to be recovered through alternative arrangements. |
C.2.3 | The contractor’s marketing and sales costs should not be included as bid costs and should be treated separately under C.1 of this guidance. |
D.3.2 | Development costs that are recognised as an intangible asset and amortised are dealt with in section G.1 of this guidance. |
SSRO Opinion: In 2016 the SSRO issued an opinion on various matters related to risk, including the extent to which the cost for re-work and defects and deficiencies were Allowable Costs in a qualifying defence contract. Link to full referral |
SSRO Determination: In 2022 the SSRO issued a determination on on the treatment of Research and Development Expenditure Credit when determining allowable costs under a qualifying defence contract. Link to full referral |
E.5.2 | The costs of insurance may be considered to enable the performance of the QDC or QSC in question when:
|
E.5.7 | Where such costs are affected by risk or uncertainty the parties should have regard to the guidance in Part H when determining whether the costs are Allowable Cost. |
F.1.1 | This guidance is applicable to all contract discussions between the Secretary of State and contractors regarding Allowable Costs in regard to QDCs and QSCs. Whilst the majority of discussions about whether costs are appropriate, attributable to the contract and reasonable in the circumstances will be resolved without reference to further guidance there are a number of more complex issues that arise that may require additional guidance and this should be sought from the SSRO if agreement cannot be reached between the Secretary of State and the contractor. |
F.1.3 | In all cases of an exceptional nature which result in separate negotiations the SSRO should be informed. |
F.3.4 | Any decision on whether such costs are Allowable must be subject to a separate agreement between the contractor and the Secretary of State, to which the contractor is to provide the relevant evidence to support the payment. Any such agreement is to be separately reported to the SSRO with the necessary evidence to support the agreement. |
F.4.1 | Sunk costs are costs that that have been incurred, and committed costs are costs that have already been agreed to be incurred, at the time a contract becomes a qualifying contract. Sunk and committed cost may include, for example, bid costs (See C.2) or the cost of work undertaken at risk. SSRO Opinion: In 2018 the SSRO issued an opinion on the extent to which costs agreed prior to conversion of a contract to a qualifying defence contract may be Allowable Link to full referral SSRO Opinion: In 2016 the SSRO issued an opinion on Allowable Costs arising from work undertaken at risk in respect of a proposed qualifying defence contract. Link to full referral |
F.4.3 | If a contract becomes a qualifying contract following an amendment, sunk and committed costs may relate to goods, works, or services provided under the original contract. The SSRO expects that the parties would make appropriate arrangements such that it should be unnecessary for any question to be raised with the SSRO in relation to any sunk costs. Such arrangements may include stating in the amended contract that: |
G.1.1 | This section is concerned with tangible and intangible assets that have been recorded in the contractor’s balance sheet and in respect of which the contractor seeks to charge costs under a QDC. The following are examples of these assets:
|
G.1.4 | Depreciation and amortisation should not be Allowable in respect of an asset if the costs of the asset have already been recovered from the MOD. For example, if the MOD pays for a tangible asset at or before the start of the contract it should not pay additional costs in the form of depreciation in relation to that asset while the contract is being delivered. |
G.1.5 | If the MOD retains ownership of an asset and makes it available to the contractor in order for it to deliver the contract, depreciation and amortisation should not be Allowable Costs. |
G.1.7 | If a contractor’s application of its own accounting policies results in a change in the valuation of an asset (for example, through a re-valuation or an impairment review), this may also result in a change in non-cash costs such as depreciation and amortisation, or a new non-cash cost (for example, an impairment expense or gain). Such circumstances will require a case-by-case review to understand why the value has changed, whether the MOD is due any balancing credit and ensure that any costs are reasonable in the circumstances. |
G.2.1 | Borrowing costs are generally not Allowable Costs. The approach to calculating the step 6 capital servicing adjustment compensates contractors for these costs. The SSRO publishes separate guidance on how the step 6 capital servicing adjustment ensures the contractor receives an appropriate and reasonable return on the fixed and working capital it employs for the purpose of enabling it to perform the contract. SSRO guidance: Capital servicing adjustment |
SSRO Opinion: In 2016 the SSRO issued an opinion on various matters related to risk, including the extent to which the cost for re-work and defects and deficiencies were Allowable Costs in a qualifying defence contract. Link to full referral |
H.1.3 | In determining an estimate of the total Allowable Costs for the contract the parties should consider:
|
H.1.4 | For a contractor’s estimated costs to be Allowable Costs the estimate should aim to anticipate the actual Allowable Costs the contractor will incur in performing the contract, taking account of risk or uncertainty. There should be economy and efficiency in the use of resources, unless there is a clear reason to the contrary [see 3.13 d]. The contractor should seek opportunities for risk reduction or increased efficiency to be captured through the life of the contract. |
H.1.8 | The relevant parties should take a proportionate approach to determining what type and standard of information is required about risk or uncertainty in order to be satisfied that estimated costs are Allowable Costs, having regard to the guidance at paragraph 2.6. |
H.2.2 | The term ‘risk contingency element’ is adopted as the legislation requires contractors to report any risk contingency element within the Allowable Costs of a QDC or QSC. Contracting parties may use alternative terms to describe cost items set out in H 2.1, for example, ‘risk allowance’; ‘contingency’; or ‘management reserve’. This should not alter the substantive interpretation or application of this guidance. |
H.2.4 | The approach or approaches to be taken when quantifying a risk contingency element in costs should be appropriate to the circumstances of the case, having regard to the guidance at H.1.3 to H.1.7. |
H.2.6 | The SSRO provides separate guidance for contractors on the reporting of data on any element of risk contingency in Allowable Costs. |
H.3.5 | More specific guidance on determining whether the costs of insurance are Allowable Costs is provided in Part E.5. |
H.4.1 | Cost risk is the possibility that the actual amount of costs which are determined to be Allowable Costs will differ from the estimated amount of those costs. The presence of cost risk may be reflected through the agreement of a cost risk adjustment in determining the contract profit rate for a QDC or QSC. The cost risk adjustment should not be used to include within the contract price any element of the estimated costs that have been identified, as these should be considered in the determination of the estimated Allowable Costs. The SSRO provides separate specific guidance on cost risk adjustment. SSRO guidance: Cost risk adjustment |