Part 3: Pricing of contracts
Contents: Part 3 makes provision for determining the price payable under a qualifying defence contract. Qualifying defence contracts must be priced according to a formula set out in section 15(4) of the Act. There are many different types of commercial arrangement used for qualifying defence contracts, and regulations 10 and 11 accommodate them by allowing the costs which are an element in the formula to be estimated at different times, and in various combinations of actual and estimated costs, leading to six “regulated pricing methods”. Parties to a contract may agree which of the regulated pricing methods is to be used for that contract (regulation 10(2)). Part 3 also prescribes the procedure for the SSRO to make determinations about contract profit rate adjustments (regulation 18) and allowable costs (regulation 19).
Power conferred by: Section 15(1) |
(a) | “CPR” is the contract profit rate for the contract, determined in accordance with regulation 11; and SSRO guidance: Contract profit rate |
(b) | “AC” means the primary contractor's allowable costs (see section 20), determined in accordance with one of the six regulated pricing methods described in paragraphs (4) to (11) below. SSRO guidance: Allowable costs |
(4) | Under the firm pricing method, the allowable costs are the allowable costs as estimated at the time of agreement. Note: The effect of the final price adjustment (section 21) is that a firm price may change if the actual outturn is significantly different from the estimate |
(5) | Under the fixed pricing method, the allowable costs are the allowable costs as—
Note: The effect of the final price adjustment (section 21) is that a fixed price may change if the actual outturn is significantly different from the estimate |
(8) | The allowable costs which are added to the product of the CPR and the allowable costs determined in accordance with paragraph (7) are the actual allowable costs determined during the contract or after the contract completion date. |
(10) | The allowable costs—
Note: The effect of the final price adjustment (section 21) is that a volume-based price may change if the actual outturn is significantly different from the estimate |
(12) | In this regulation, “specified” means specified in the contract at the time of agreement. Also refer: regulation 15 sets out the circumstances in which a target price adjustment may apply. |
Power conferred by: Section 17(1) |
(2) | Take the baseline profit rate in force at the time of agreement, which is—
SSRO guidance: Baseline profit rate |
(3) | Adjust the baseline profit rate by an agreed amount which is within a range of plus or minus 25% of the baseline profit rate, so as to reflect the risk of the primary contractor's actual allowable costs under the contract differing from its estimated allowable costs. SSRO guidance: Cost risk adjustment |
(4) | Deduct from the amount resulting from step 2 the adjustment determined in accordance with regulation 12 (“the POCO adjustment”), so as to ensure that profit arises only once in relation to those allowable costs under the contract that relate to the price payable under any group sub-contract (including any further group sub-contract). SSRO guidance: POCO adjustment |
(5) | Deduct from the amount resulting from step 3 the SSRO funding adjustment in force at the time of agreement, which is—
SSRO guidance: SSRO Funding adjustment |
(6) | Where the Secretary of State determines that the amount resulting from step 4 should be increased so as to give the primary contractor a particular financial incentive as regards the performance of provisions of the contract specified by the Secretary of State, increase that amount by an amount (“the incentive adjustment”) specified by the Secretary of State, that amount not to exceed two percentage points. SSRO guidance: Incentive adjustment |
(9) | The capital servicing rates are—
SSRO guidance: Capital servicing adjustment |
Power conferred by: Section 17(2) |
SSRO guidance: POCO adjustment |
(2) | Where paragraph (1) applies to a qualifying defence contract, and the Secretary of State is satisfied that—
the POCO adjustment is zero. |
(3) | Where paragraph (1) applies to a qualifying defence contract, and the Secretary of State is not satisfied of the matters described in paragraph (2)—
|
(4) | Where paragraph (1) does not apply to a qualifying defence contract, the POCO adjustment is zero. |
(5) | “Group sub-contract” means a contract—
|
(6) | “Further group sub-contract” means a contract—
|
(8) | Attributable profit does not include—
|
(9) | In determining the value of a contract for the purposes of sub-paragraph (5)(c) or (6)(c) (as the case may be), paragraphs (5) to (12) of regulation 5 do not apply. |
Power conferred by: Section 18(2)(c) |
(2) | The prospective contractor and the Secretary of State may agree an amount which may be used as the cost risk adjustment (regulation 11(3)) for any qualifying defence contract entered into between the prospective contractor and the Secretary of State within the relevant year, so as to reflect the risk of the primary contractor's actual allowable costs under [F1any such qualifying defence contract] differing from its estimated allowable costs. |
(3) | An amount agreed under paragraph (2) must be within a range of plus or minus 25% of the baseline profit rate. |
(4) | The prospective contractor and the Secretary of State may agree an amount which may be used as the POCO adjustment (regulation 12(3)) for any qualifying defence contract entered into between the prospective contractor and the Secretary of State within the relevant year, so as to ensure that profit arises only once in relation to those allowable costs under [F2any such qualifying defence contract] that relate to the price payable under any group-sub-contract (including any further group sub-contract). |
(5) | The prospective contractor and the Secretary of State may agree an amount which may be used as the capital servicing adjustment (regulation 11(7)) for any qualifying defence contract entered into between the prospective contractor and the Secretary of State within the relevant year, so as to ensure that the primary contractor receives an appropriate and reasonable return on the fixed and working capital employed by the primary contractor for the purposes of enabling the primary contractor to perform [F3any such qualifying defence contract]. |
(6) | In agreeing a capital servicing adjustment under paragraph (5), the prospective contractor and the Secretary of State must—
|
Power conferred by: Section 15(3) |
[F4The Schedule makes provision for the re-determination of the contract price for a qualifying defence contract.] |
Power conferred by: Section 16(1) |
The circumstances specified for the purposes of section 16(1) are that—
|
Power conferred by: Section 21(1) |
(1) | The amount specified for the purposes of section 21(4)(b) (value of qualifying defence contract of or above which this regulation applies) is £5,000,000, and an adjustment may be made to the total price payable by the Secretary of State under a qualifying defence contract (“final price adjustment”) if either—
|
(2) | The amount specified for the purposes of section 21(5)(b) (value below which direction excluding final price adjustment may be made) is £50,000,000. |
(2A) | [F5Where the price payable under the contract includes one or more defined components which use a regulated pricing method other than the firm pricing method, fixed pricing method, or volume-driven pricing method, the value of such component or components shall be disregarded for the purposes of paragraph (2).] |
(3) | The matter specified for the purposes of section 21(6) (matters to which the Secretary of State must have regard in deciding whether to make such a direction) is the effect that making a direction might have on the terms of any subsequent contract that the Secretary of State expects to enter into with that primary contractor. |
(5) | The Secretary of State may, within—
whichever is the sooner, notify the primary contractor that the Secretary of State intends to make a final price adjustment. |
(7) | Where a notice is given under paragraph (5) or (6), the Secretary of State and the primary contractor must attempt to agree the amount of the final price adjustment, but if they are unable to reach an agreement either the Secretary of State or the primary contractor may refer the matter to the SSRO for determination. |
(8) | A reference under paragraph (7) may be made—
|
(9) | In making a determination, the SSRO must have regard to—
|
Power conferred by: Section 21(2) |
(1) | Where the outturn profit rate exceeds the contract profit rate, the final price adjustment is to be calculated in accordance with whichever of paragraphs (2) to (4) applies. |
(6) | In this regulation—
Info: Refer Regulation 66: where the contract is a Qualifying sub-contract the final price adjustment does not adjust the price; rather, a payment is made directly to or from the Secretary of State. |
Power conferred by: Section 18(3) |
SSRO guidance: Determinations |
(1) | This regulation applies to any adjustment that has been agreed under step 2, 3 or 6 in regulation 11 (including an adjustment agreed on a group basis under regulation 13). |
(2) | The SSRO may, on an application by the Secretary of State or the primary contractor made within two years after the contract completion date, determine whether the amount of the adjustment is appropriate. |
(3) | In making a determination, the SSRO must have regard to—
at the time of agreement. |
(4) | In making a determination that relates to the amount of an adjustment agreed under step 2 (cost risk adjustment), the SSRO must have regard to the terms of the contract. |
(5) | If the SSRO determines that the amount of the adjustment was not appropriate, it may determine that the contract price is to be adjusted by a specified amount. |
Power conferred by: Section 20(5) |
SSRO guidance: Determinations |
(1) | The Secretary of State may not make an application under section 20(5) for a determination of the extent to which a particular cost is an allowable cost unless—
|
(3) | In making a determination, the SSRO must have regard to—
|