Pricing of contracts
Contents: These sections of the Defence Reform Act describe how a qualifying contract should priced, including the pricing formula, the contract profit rate, the determination of 'allowable costs' and the final price adjustment, and permits the Secretary of State to make regulations to implement aspects of the regime.
(1) | Single source contract regulations must make provision about determining the price payable under a qualifying defence contract to the primary contractor [Refer: regulation 10] . |
(2) | The regulations must provide for the price payable under the contract to be determined in accordance with the formula in subsection (4) [Refer: regulation 10(1)] . |
(3) | The regulations must provide that where the Secretary of State and the primary contractor propose to amend the contract in a way that would affect the price determined by virtue of subsection (2) or this subsection—
|
(4) | The formula is— where—
|
(5) | The regulations may provide for a determination by virtue of subsection (2) or (3) to be made at such times as may be specified in the regulations (and different times may be specified for different kinds of contract) [Note: There are 6 regulated pricing methods set out inregulation 10]. |
(1) | Single source contract regulations may specify circumstances in which, if the Secretary of State and the primary contractor so agree—
|
(2) | The amount of any adjustment by virtue of subsection (1)(b) must be determined—
SSRO guidance: Referrals procedures for determinations |
(3) | Section 21 (final price adjustment) does not apply to a contract in a case where an agreement of a kind mentioned in subsection (1) has effect. |
(1) | Single source contract regulations must make provision for determining the contract profit rate for a qualifying defence contract [Refer: regulation 11] . |
(2) | The regulations must provide for the determination to be made by taking the following sequence of steps, subject to section 18(2)— |
Take the baseline profit rate (see section 19) which is in force at the relevant time. “The relevant time” means—
SSRO guidance: Baseline profit rate |
Adjust that rate by an agreed amount, being an amount falling within specified parameters above or below the baseline profit rate [Refer: regulation 11(3): +/- 25% of the baseline profit rate], so as to reflect the risk of the primary contractor's actual allowable costs under the contract differing from its estimated allowable costs. “Specified” means specified in the regulations. SSRO guidance: Cost risk adjustment |
Deduct an agreed amount from the amount resulting from step 2, so as to ensure that profit arises only once in relation to those allowable costs under the contract in respect of which the regulations provide [Refer: regulation 11(4)] that a deduction may be made (and see section 20 as to allowable costs). SSRO guidance: POCO adjustment |
Deduct the SSRO funding adjustment (see section 19) which is in force at the time mentioned in step 1 from the amount resulting from step 3 [Refer: regulation 11(5). SSRO guidance: SSRO Funding adjustment |
Where the Secretary of State determines that the amount resulting from step 4 should be increased so as to give the primary contractor a particular financial incentive as regards the performance of provisions of the contract specified by the Secretary of State, increase that amount by an amount specified by the Secretary of State. Any increase must not exceed the maximum increase permitted by the regulations. [Refer: regulation 11(6): 2 percentage points] SSRO guidance: Incentive adjustment |
Take the amount resulting from step 5 and add to or subtract from it an agreed amount, so as to ensure that the primary contractor receives an appropriate and reasonable return on the fixed and working capital employed by the primary contractor for the purposes of enabling the primary contractor to perform the contract. This adjustment—
SSRO guidance: Capital servicing adjustment |
(3) | The contract profit rate is—
|
(4) | For the purposes of subsection (2)—
|
(1) | The Secretary of State or an authorised person, and the primary contractor, must have regard to guidance issued by the SSRO in relation to any of the steps set out in section 17(2). SSRO guidance: Profit rate guidance |
(a) | disapply the requirement to take any or all of steps 2 to 6 in section 17(2) in relation to a qualifying defence contract the value of which is less than the amount specified for the purposes of this paragraph [Note: this power is not used]; |
(c) | where the Secretary of State is a party to a group of qualifying defence contracts with the same primary contractor, provide for section 17(2) to apply in relation to those contracts—
|
(3) | Single source contract regulations may provide that the SSRO—
SSRO guidance: Referrals guidance |
(4) | The following persons are within this subsection—
|
(2) | For the purpose of assisting the Secretary of State in determining for a financial year each of the rates mentioned in subsection (1) and the SSRO funding adjustment, the SSRO must provide the Secretary of State with its assessment of what is the appropriate rate or funding adjustment for that year. Info: The SSRO's rates methodology is available on its website.
|
(3) | The SSRO—
|
(4) | The Secretary of State must publish each of the rates mentioned in subsection (1) for a financial year, and the SSRO funding adjustment for that year, in the London Gazette no later than 15 March in the preceding financial year.
|
(5) | Subsection (6) applies if, in the case of a particular rate or the SSRO funding adjustment, there is a difference between the rate or funding adjustment determined under subsection (1) and the SSRO's assessment of the appropriate rate or funding adjustment for the financial year in question. |
(3) | Single source contract regulations may provide that the SSRO
|
(1) | The SSRO must issue guidance about determining whether costs are allowable costs under qualifying defence contracts. SSRO guidance: Allowable Costs guidance |
(3) | In determining whether the requirements set out in subsection (2)(a) to (c) are met in relation to a particular cost, the Secretary of State or an authorised person, and the primary contractor, must have regard to guidance issued under subsection (1). |
(4) | The Secretary of State or an authorised person may at any time require a primary contractor to show [also refer: section 23(5) examination of records] (whether by reference to guidance issued under subsection (1) or otherwise) that the requirements set out in subsection (2)(a) to (c) are met in relation to a particular cost claimed by the primary contractor as an allowable cost under a qualifying defence contract. |
(5) | The SSRO may determine the extent to which a particular cost is an allowable cost under a qualifying defence contract where the Secretary of State, an authorised person or the primary contractor applies to the SSRO for such a determination [Refer: regulation 19 for additional requirements]. SSRO guidance: Referral procedures |
(6) | The SSRO may determine that the price payable under the contract is to be adjusted by an amount specified by the SSRO in consequence of a determination under subsection (5), having regard to the extent to which the cost in question was treated as an allowable cost when the price payable under the contract was determined (or last determined) in accordance with section 15. |
(1) | Single source contract regulations may provide for adjustments to be made to the total price payable by the Secretary of State under a qualifying defence contract [Refer: regulation 16] . |
(2) | The regulations must specify the procedure to be followed in determining the amount of any adjustment [Refer: regulation 17] . |
(3) | Provision made under subsection (2) must include provision for the amount of any adjustment to be determined—
|
(4) | Provision under this section may be expressed so as to apply—
|
(5) | The Secretary of State may direct that provision under this section does not apply in relation to a qualifying defence contract the value of which is—
|
(6) | The regulations may specify matters to which the Secretary of State must have regard in deciding whether to make a direction under subsection (5) [Refer: regulation 16(3): the effect that making a direction might have on the terms of any subsequent contract that the Secretary of State expects to enter into with that primary contractor]. |
(1) | This section applies where—
|
(2) | If all or part of the amount mentioned in subsection (1)(b)(i) or (ii) is not paid or repaid before the payment date, the unpaid balance carries interest from that date at the rate for the time being specified in section 17 of the Judgments Act 1838 [8 percent per annual]. |
(3) | The “payment date” is the date determined by the SSRO, in making the determination in question, as the date by which the amount must be paid or repaid. |
(4) | The person to whom the amount is required to be paid or repaid (“the creditor”) may recover from the other person as a debt due to the creditor the unpaid balance and any unpaid interest. Info: This section does not explicitly apply to determinations made by virtue of section 16(2)(b) (the amount of a target price adjustment), or section 35(7) (determinations that would have been carried out by the Review Board for Government Contracts). |